October 2017
Addition of a number of further key pieces of equipment to the ADENCO fleet, including three large diameter poly welding machines.
Company News
August 2017
Award and commencement of the Eastern Ridge Potable Water Pipeline Replacement Project FOR BHP.
New Project Awarded
August 2017
Award and commencement of the JB WHASH Surplus Pipeline Project at BHP’s Jimblebar Mine Site.
New Project Awarded
July 2017
Award and commencement of the SD - Flare Pit Erosion Rehabilitation Project at BHP Billiton Petroleum’s Macedon Gas Plant.
New Project Awarded
July 2017
ADENCO receives BHP Environmental award at the 2017 Contractor Health, Safety, Environment and Community Performance Awards night in Newman.
Company News


June 2017
ADENCO reaches a significant milestone with another safe year and over 100,000 man hours incident & injury free across all projects.
Safety Update
June 2017
Achieved over 10,000 man hours incident and injury free on the BHP RAV project.
Safety Update
May 2017
Safe completion of the 35km Water Transfer Pipeline for GRES at the Gruyere JV Gold Mine (Gold Fields Ltd & Gold Road Resources JV).
Over 3500 man hours incident and injury free.
Safe Completion
May 2017
ADENCO achieves certification for ISO9001:2015 Quality, ISO14001:2015 Environmental and AS/NZS4801:2001 OHS Management System Standards.
Company News
April 2017
Award and commencement of the 35km Water Transfer Pipeline for GRES at the Gruyere JV Gold Mine (Gold Fields Ltd & Gold Road Resources JV).
New Project Awarded
March 2017
Mobilisation and commencement of the RAV Mine Site Infiltration Ponds System for BHP at MAC
New Project Awarded
February 2017
Safe completion of the OB29 Inpit Dewatering Project at Mt Whaleback Mine Site.
Over 4000 man hours incident and injury free.
Safe Completion
February 2017
Award of the RAV Mine Site Infiltration Ponds System for BHP at MAC
New Project Awarded
January 2017
Achieved 70,000 man hours incident free across all projects.
Safety Update
December 2016
Safe completion of the Creek Crossing Project at a Major Iron Ore Mine Site, Pilbara WA
Safe Completion
November 2016
Award and commencement of the OB29 Inpit Dewatering Project at Mt Whaleback Mine Site
New Project Awarded
November 2016
Achieved 60,000 man hours incident free across all projects.
Safety Update
November 2016
Award and commencement of the PC3 Creek Crossing Project at Jimblebar Mine Site
New Project Awarded
October 2016
Addition of Newman base to ADENCO portfolio including the acquisition of several key pieces of earthmoving equipment
Company News
October 2016
Safe completion of the OB35 Inpit Dewatering Project at Mt Whaleback Mine Site
Safe Completion