Newman Water Treatment Plant

Scope

Install of 7km of DN355 PN12.5 Reject Discharge Main Pipeline at MT Whaleback

Location

Iron Ore Mine Site
Pilbara WA
Testimonial

Install of 7km of DN355 PN12.5 Reject Discharge Main Pipeline at MT Whaleback

Description

Supply of all labour, plant, equipment and supervision to complete the install of 7km of DN355 PN12.5 Pipeline at MT Whaleback for UON / BHP. The works also included survey works, the installation of 340m of DN560 black polyethylene pipe for trenched road crossing sleeves, installation of fittings and valves, trenchless horizontal directional drilling beneath a roadway, railway and gas main with all associated civil works. The works were carried out over a 6 week period where both safety and quality exceeded the Client's expectations.

Map of Australia
Located In Perth     Western Australia